How a basement is built: underpinning and retaining walls

A basement is built using an engineered sequence that keeps the existing building and surrounding ground supported while the new enclosure is formed. Underpinning can extend support beneath existing foundations, while retaining walls resist the surrounding ground; the correct combination depends on the site.

A basement is built through an engineered sequence that maintains support to the building and surrounding ground while the new enclosure is formed. Underpinning is one way of extending support beneath existing foundations, but it is not a universal solution or a safe excavation method to improvise on site. [1] [2]

Establish the starting conditions

Before designing the work, the team needs information about the existing structure, foundations, ground and nearby services. The scope of investigation should answer the engineer's questions, rather than consist only of a measured drawing of the rooms above. Basement planning guidance also expects the proposed construction to be supported by appropriate ground and structural evidence. [3] [4]

The design must consider neighbouring buildings as well as the client's house. HSE warns that excavation can undermine nearby structures and that temporary support may be needed before work proceeds. [5]

Underpinning and retaining structures

Underpinning transfers or extends support below an existing foundation. A retaining structure has to support the surrounding ground and associated pressures. In a basement, the permanent structure and temporary works need to be designed as a coordinated arrangement rather than separately assumed to support one another. [1] [6]

The selected solution may involve a sequence of local underpinning works, a different retaining system or a combination. The engineer determines the appropriate method, working limits and checks. An internet sketch of typical underpinning does not establish a safe sequence for a particular London terrace. [1]

The main project stages

Although the detailed order varies, the construction plan should address:

  1. site preparation, service checks and protection of existing structures;
  2. installation of the required temporary support;
  3. controlled excavation and construction of the permanent foundations and enclosure;
  4. coordinated waterproofing, drainage and service installation;
  5. inspections, testing and completion of the internal fit-out.

This is a homeowner's outline, not an instruction for carrying out excavation. The contractor's method and the engineer's design must define the actual sequence. [5] [6] [7]

Water and stability must be considered together

Water entering an excavation is not simply a housekeeping issue. HSE identifies the need to control water and maintain excavation stability, including the effects of pumping. The final basement's waterproofing must also suit the anticipated conditions and intended internal environment. [5] [8]

Agree penetrations, joints and the connection between walls and floor before those elements are built. Waterproofing protection can be compromised where different parts of the construction are detailed independently. [9] [10]

Inspection points and changes

LABC's underpinning guidance explains that building control needs to inspect underpinning work, including the relevant sections before concrete is placed. The programme should include those inspection points; photographs alone should not be assumed to replace the agreed visits. [11]

Unexpected foundations or ground conditions should be referred back to the responsible designer. HSE's guidance requires support arrangements to remain suitable as the work proceeds, so a contractor should not treat the original sequence as permission to continue regardless of what is exposed. [2]

Before work starts, ask who controls design changes, who inspects temporary works and who has authority to stop progress at an unresolved stage. Those responsibilities are as important to understanding the build as the name of the foundation system. [6] [12]

Sources 12 references
[1]
Underpinning: good practice guidance, June 2023

Temporary Works Forum / ASUC · accessed 2 Oct 2026

[2]
Structural stability during alteration, demolition and dismantling

Health and Safety Executive · accessed 2 Oct 2026

[3]
Camden Planning Guidance: Basements, January 2021

London Borough of Camden · accessed 2 Oct 2026

[4]
Basement Development Supplementary Planning Document, January 2016

London Borough of Islington · accessed 2 Oct 2026

[5]
Excavations

Health and Safety Executive · accessed 2 Oct 2026

[6]
Temporary works

Health and Safety Executive · accessed 2 Oct 2026

[7]
Structural waterproofing guidance

Property Care Association · accessed 2 Oct 2026

[8]
Waterproofing and tanking advice for homeowners

Property Care Association · accessed 2 Oct 2026

[9]
Best Practice Guidance: Type A Waterproofing Systems

Property Care Association · accessed 2 Oct 2026

[10]
Best Practice Guidance: Type B Waterproofing Systems

Property Care Association · accessed 2 Oct 2026

[11]
[12]
Design and building work: meeting building requirements

Building Safety Regulator / HSE · accessed 2 Oct 2026