Opening up the back of a house normally needs an engineer to design how the loads formerly carried by the wall will be supported. The solution may involve a steel beam, columns and foundation work; the beam cannot safely be selected from the opening width alone.

IStructE describes the engineer's role as establishing the structure and safely redistributing loads when walls are removed. [1]

What information does the engineer need?

Provide the existing and proposed plans, any earlier structural drawings and information about previous alterations or movement. The engineer may need to inspect and investigate concealed construction before deciding which parts of the wall and foundations can be relied upon. [1]

Show the desired clear opening, ceiling arrangement and door positions. Ask how the proposed structure will affect the finished room: will a downstand remain, will a column project into the space, and how will the support meet the floor and roof? These are design questions to resolve before kitchen and glazing orders are placed.

The supports matter as much as the beam

The engineer calculates the new elements and the load path to suitable foundations. A beam resting on existing masonry is not automatically an adequate arrangement; the supporting structure and ground also need consideration. Where necessary, the solution may include new columns, foundation work or a different opening arrangement. [1]

Ask the structural information to identify bearings, connections and any local support details, and to state what remains dependent on site investigation. Do not let an assumed standard detail in a quotation override a project-specific design.

Temporary support is a separate design problem

Before the wall is removed, the structure must remain stable during the work. HSE's demolition guidance requires the work to be planned and addresses structural stability and temporary support. A drawing showing the finished beam does not by itself explain how the existing house is safely supported while it is installed. [2]

Confirm who is responsible for the temporary works, installation sequence and site checks. Homeowners should not select props or an installation method from a general article; that depends on the actual structure and construction conditions.

Check fire protection and neighbouring structures

The finished design must address the fire resistance required for load-bearing elements. The specification should explain how the structural member and its supporting arrangement achieve the relevant performance, rather than relying on an unspecified promise to “box in the steel”. [3]

If a bearing or other work cuts into a party wall, the Party Wall Act can apply. Nearby new foundations may also trigger excavation notices. Resolve those procedures before the relevant work starts. [4]

Order and inspect from the correct information

IStructE specifically warns that dimensions in structural calculations are not fabrication dimensions: the contractor needs accurate site measurements before ordering steelwork. Ensure the final structural drawings, architectural dimensions and supplier information agree. [1]

Arrange the necessary building control inspections before important details are concealed, and retain the calculations and completion information. If an unexpected wall, footing or other structural condition is found, seek a revised design before proceeding. A convenient available steel section is not a substitute for that review. [5] [1]

Further published fire-guidance change

Approved Document B has a further published change taking effect on 2 September 2029, removing national fire-resistance classifications from its guidance, subject to transitional arrangements. For work around that date, check the applicable edition and the evidence supporting the specified fire-protection system. [6]

Sources 6 references
[1]
Introduction to structural engineering for domestic clients

The Institution of Structural Engineers · accessed 2 Oct 2026

[2]
Demolition

Health and Safety Executive · accessed 2 Oct 2026

[4]
The Party Wall etc. Act 1996: explanatory booklet

MHCLG / GOV.UK · accessed 2 Oct 2026

[6]
2029 amendments to Approved Document B: Fire safety

MHCLG / GOV.UK · accessed 2 Oct 2026

Contact

Need advice on your property?

Talk to our team about planning, regulations or construction.