Skip to knowledge content

Manholes inside an extension

If a public-sewer manhole lies within the proposed extension, Thames Water requires it to be relocated rather than left inside the building. A sealed internal cover is not a substitute for that requirement; agree the revised drainage and access arrangement before fixing the extension design. [1]

Identify what the chamber serves

First establish the drainage layout and whether the chamber serves a public sewer, a lateral drain or private drainage. Thames Water distinguishes its public assets from private drains, and advises using records and a site survey to identify relevant pipes. Do not assume that a chamber belongs only to your house because it sits in your garden. [1] [2]

The distinction matters because the water company's consent and access requirements must be addressed alongside the building regulations drainage design. An arrangement acceptable for one type of private drainage should not be copied as permission for a public-sewer chamber. [3] [1]

Why the chamber cannot simply disappear under the floor

Thames Water prohibits internal manholes in its build-over guidance, citing odour and flooding risks. It also needs access to maintain and repair the public sewer network. The proposal must therefore show how access will remain available after the extension is built. [1]

Avoid treating the chamber as a finishing detail to be resolved when flooring is ordered. Its position can affect the route of pipes and the relationship between drains, foundations and the external space available for access. Those relationships belong in the technical design. [3] [4]

Design the replacement arrangement

Provide the existing and proposed drainage plans, flow directions and relevant levels. Show the foundation section where it approaches the sewer. Thames Water's application checklist identifies the information it needs to assess the proposal; a planning floor plan alone may not provide it. [4] [5]

Ask the drainage designer to coordinate the proposed chamber location with the whole drainage system and required access. If relocation would need a more substantial public-sewer diversion, establish the appropriate company process instead of assuming it is a minor builder's alteration. [6]

Obtain consent before construction

Thames Water says that relocating the manhole requires the build-over application process. Planning permission does not grant this consent, and starting before the drainage arrangement is accepted risks having to change the construction. [1]

Agree the inspection sequence with building control and the water company. They have different functions, and the relevant drainage should remain available for the inspections or surveys required by each. [7] [5]

Keep the final layout

Retain a clear drawing of the completed drainage route and chamber positions together with the agreement and completion evidence. That gives future maintenance work an accurate starting point and avoids relying on the original plan after the chamber has moved. [4] [8]

Sources 8 references
[1]
Do I need a build over agreement?

Thames Water · accessed 2 Oct 2026

[2]
Where our pipes are

Thames Water · accessed 2 Oct 2026

[4]
Build over application checklist

Thames Water · accessed 2 Oct 2026

[5]
Building over sewers or public drains

Thames Water · accessed 2 Oct 2026

[6]
Diverting a sewer

Thames Water · accessed 2 Oct 2026

[7]
Starting work and inspections

Building Control Partnership, Hampshire · accessed 2 Oct 2026

[8]
Completion certificates

Cannock Chase District Council · accessed 2 Oct 2026

Contact

Need advice on your property?

Talk to our team about planning, regulations or construction.