Plan checks and approval subject to requirements

A full plans decision can approve the design, approve it subject to specified requirements, or reject it. Since the October 2023 procedural changes, the current council terminology is approval subject to “requirements”, even though older documents and conversations may refer to “conditions”. [1]

Read the actual decision

Do not treat the word “approved” as the only relevant part of the letter. Read the approved drawing references, the description of the work and any requirements attached to the decision. Establish which documents form the accepted package and whether further information or modifications are still needed. [1] [2]

A full plans decision concerns the submitted design. It is not a completion certificate and does not confirm that future work will necessarily be built correctly. The construction still needs appropriate inspections and final evidence. [3] [4]

Turn requirements into an action list

For each outstanding item, identify who will supply the information, what document needs revising and when the relevant work is due on site. Keep the council's response with the revised document so the builder is not working from an earlier issue.

This is particularly useful for structural details, drainage arrangements and product specifications that may be completed by different members of the team. The designer and contractor retain their compliance duties; the inspector is not responsible for producing the missing design. [5] [6]

Do not confuse building control requirements with planning conditions

Planning and building regulations are separate systems. A building control decision does not discharge a planning condition, and a planning approval does not settle the technical matters raised by building control. Keep two separate schedules where both approval processes have outstanding items. [7]

Similarly, a Thames Water agreement can impose a separate technical arrangement for a sewer. Check that the building control drawings and the sewer submission describe the same proposed construction. [8] [9]

What happens if the plans are rejected?

Read the stated reasons and ask the designer to revise the affected details or provide the missing evidence. Do not assume rejection means that the project is unacceptable in planning terms: it concerns the building regulations submission. Conversely, do not start the disputed detail on the assumption that inspection will make an inadequate design acceptable. [3] [2]

Changes after the decision

Use a revision record and notify the building control body of relevant changes. A product substitution or site alteration can affect more than one requirement, so coordinate the revised design before carrying it out. [5]

For private building control, the initial notice is a separate procedural document and should not be mistaken for a council full plans decision. Check whether any later plan-approval changes have taken effect before choosing your application route. [10] [11]

Sources 11 references
[1]
[2]
Pre-site approval: full plans

Planning Portal · accessed 2 Oct 2026

[3]
[4]
Completion certificates

Cannock Chase District Council · accessed 2 Oct 2026

[5]
Design and building work: meeting building requirements

Building Safety Regulator / GOV.UK · accessed 2 Oct 2026

[6]
About building control site visits

London Borough of Richmond upon Thames · accessed 2 Oct 2026

[7]
Building regulations approval

GOV.UK · accessed 2 Oct 2026

[8]
Build over application checklist

Thames Water · accessed 2 Oct 2026

[9]
Do I need a build over agreement?

Thames Water · accessed 2 Oct 2026

[10]
Building control: initial notices

London Borough of Newham · accessed 2 Oct 2026

Contact

Need advice on your property?

Talk to our team about planning, regulations or construction.