Skip to knowledge content

Construction management plans required by London boroughs

A construction management plan explains how the building work will be organised to limit disruption and protect surrounding streets and neighbours. London councils may require one through a planning condition, so check whether it must be approved before any work starts.

Camden and Redbridge publish their own requirements; there is no single document that automatically satisfies every borough. [1] [2]

Read the actual planning condition

Identify the condition’s trigger, the documents required and the procedure for approval. A requirement to submit a plan is not necessarily satisfied by emailing a draft to the planning officer. Camden explains that a required construction management plan must be approved before the development starts. [1]

Redbridge assesses the need for a plan according to the development and its likely effects, including highway and amenity impacts. Do not assume a small site is automatically exempt, or that every domestic alteration needs the same level of submission. [2]

Make it specific to the site

Start with the council’s current template where one is provided. The information should explain the practical arrangements for the project rather than repeat general promises about being considerate. Camden’s process addresses matters including deliveries, traffic, site activity and consultation with neighbours. [1]

For your own review, ask the contractor to show how the proposed arrangement works on the busiest day: where a delivery vehicle waits, how materials reach the work area and who keeps pedestrians away from the operation. Ask for unresolved assumptions to be listed before the plan is submitted.

Coordinate the separate plans and permissions

A planning construction management plan is not the same as the CDM construction phase plan. The latter is a health-and-safety document required before the construction phase. Both need to reflect the work, but approval of one does not replace preparation of the other. [3]

Similarly, highway structures and occupation of parking bays have separate licensing processes. Check that a delivery or scaffold arrangement described in the management plan is also authorised through the relevant highway or parking procedure. [4] [5]

Give someone responsibility for delivery

Before signing the building contract, identify who prepares the plan, obtains approval, pays associated charges and manages compliance on site. Redbridge explains that an approved plan forms part of the requirements controlling construction. It should therefore be included in the contractor’s working information rather than left in the planning file. [2]

Keep the approved version, consultation record and site contact details together. When the programme or access arrangements change, ask the planning team whether a revised approval is needed before departing from the agreed plan. The objective is to keep the real construction method aligned with the approved arrangements, not merely to obtain a document once.

Sources 5 references
[1]
About construction management plans

London Borough of Camden · accessed 2 Oct 2026

[2]
Construction management plans

London Borough of Redbridge · accessed 2 Oct 2026

[4]
Building licence

London Borough of Camden · accessed 2 Oct 2026

[5]
Parking bay suspensions

London Borough of Camden · accessed 2 Oct 2026

Contact

Need advice on your property?

Talk to our team about planning, regulations or construction.