Deposits, stage payments and valuations

Agree deposits and stage payments before work starts, linking them to clear deliverables and a process for checking the amount due. A payment request, a valuation of completed work and an advance for future goods are different things.

JCT's homeowner guidance calls for an agreed payment schedule, and RICS explains how interim valuations assess value under the contract. [1] [2]

Explain what the deposit buys

Request a breakdown of any deposit: design work, a specifically identified order or mobilisation. Ask when it becomes payable and what happens if the job does not proceed. Do not infer that a deposit is protected simply because the contractor issues a receipt. Consumer guidance recommends avoiding large advance payments and keeping records of payments made. [3]

Where a significant product is manufactured away from site, ask who owns it, where it is stored and what insurance and security apply. A payment for a future window order is not evidence that the windows already exist or belong to you. RICS discusses these distinctions when valuing off-site goods. [2]

Define the stages precisely

Replace a vague milestone such as “roof done” with a description you and the contractor can check against the work. Ask who will inspect it and what evidence accompanies the request. Request a sample payment statement showing the proposed treatment of approved changes and earlier payments.

Keep a payment register showing each request, assessment, amount paid, date and supporting document. Put the contract’s notice and payment dates in a calendar and ask the appointed adviser who must act at each point. Confirm any disputed assessment in writing instead of relying on a site conversation.

Know which payment regime applies

Ordinary owner-occupier work is not automatically subject to the Construction Act's payment and adjudication machinery. The residential-occupier exception is fact-sensitive; business development and rental work must not simply be treated as identical to a project for your own residence. [4]

The Commercial Payments Bill proposes reforms, but remains a bill as at 2 October 2026. Do not apply proposed payment periods or a proposed retention ban as though they already override your contract. [5]

Understand card protection accurately

Section 75 protection can apply where the relevant cash price is more than £100 and not more than £30,000, subject to the required consumer-credit relationship and other conditions. Paying only part by credit card can qualify, but the cash price—not the amount put on the card—controls that price test. A small card deposit does not automatically protect an entire higher-value building contract. [6]

Chargeback is a separate card-scheme process with conditions and deadlines. Contact the provider promptly when a payment problem arises; neither route guarantees recovery in every case. [6]

Sources 6 references
[1]
Home Owner Contracts

The Joint Contracts Tribunal · accessed 2 Oct 2026

[2]
[3]
Before you get building work done

Citizens Advice · accessed 2 Oct 2026

[4]
RBH Building Contractors Limited v Ashley James & Anor [2026] EWCA Civ 511, 29 April 2026

Court of Appeal / The National Archives · accessed 2 Oct 2026

[5]
Commercial Payments Bill [HL]: bill progress

UK Parliament · accessed 2 Oct 2026

[6]
Problems with goods and services: section 75 and chargeback

Financial Ombudsman Service · accessed 2 Oct 2026

Contact

Need advice on your property?

Talk to our team about planning, regulations or construction.